NEEDS

pime1
  • SAVE COSTS: The primary energy consumption in an SME is produced by lighting and climatization equipments and office automation, representing almost 90% of it.
  • CONSUMPTION CONTROL: Having such consumption under control, will reduce your electricity bill up to 25%.
  • AVOID LOSSES: Analyze the characteristics of buildings and identify where the most important energy leaks. For walls, windows and roofs loses over 30% of energy.
  • INCREASE COMFORT: Make the temperature, humidity and air exchange to give a better sense of comfort to the user and the worker.

SOLUTIONS

  • MONITORING FACILITIES: Control lighting and climatization consumption of your office easily, remotely and centrally in real time.pime4
  • SURROUNDING IMPROVEMENT: Increase the insulation of facades and roofs, inside or outside. Changing old wooden windows and balconies  unsealed.
  • ADJUST TIMES AND CONSUMPTION: Avoid maximum power at certain times.
  • SUBSTITUIR INSTAL·LACIONS POC EFICIENTS: Aparells amb molta demanda energètica.
  • REPLACE INEFFICIENT FACILITIES: Items with high demand of energy.

ACHIEVEMENTS

pime5
  • ENERGY DEMAND REDUCTION: Reducing energy demand by an average of 30%.

USE CASE: REPORT ON THE CONSUMPTION OF AN OFFICE BUILDING

OFFICE BUILDING 5.000m2: ENERGY INVOICE €135.000 / year.




ENERGY INVOICE
INSTALLATION CONSUMPTION ENERGY BILL
Climate Control and Ventilation 64.000€
Indoor and Outdoor lighting 35.000€
Computers, CPD, Copiers 17.000€
Elevators and hoist 8.000€
Water plumbing 6.000€
Vending, fire prevention 5.000€
TOTAL 135.000€

ACTIONS AND COSTS TO ACHIEVE SAVINGS
ACTIONS COSTS €/M2 ESTIMATED SAVING(%) ANNUAL SAVING(€) ROI (YEARS)
Change user habits 0 5 6.750€ IMMEDIATE
Change vending machines 0 5 6.750€ IMMEDIATE
Presence control for lighting 15 10 13.500€ 1-2
Presence control for air conditioning 15 10 13.500€ 1-2
Manage outer solar protection 5 10 13.500€ 2-3
Include outer sunscreen 100 15 20.250€ 3-4
Integration of installations 20 10 13.500€ 3-4
Change luminaries 30 15 20.250€ 5-6
Change climate machines 250 15 20.250€ 10-11
Change elevators UD. 5 6.750€ +10
Facade comprehensive reform 600* 25 27.000€ +10