NEEDS

- SAVE COSTS: The primary energy consumption in an SME is produced by lighting and climatization equipments and office automation, representing almost 90% of it.
- CONSUMPTION CONTROL: Having such consumption under control, will reduce your electricity bill up to 25%.
- AVOID LOSSES: Analyze the characteristics of buildings and identify where the most important energy leaks. For walls, windows and roofs loses over 30% of energy.
- INCREASE COMFORT: Make the temperature, humidity and air exchange to give a better sense of comfort to the user and the worker.
SOLUTIONS
- MONITORING FACILITIES: Control lighting and climatization consumption of your office easily, remotely and centrally in real time.
- SURROUNDING IMPROVEMENT: Increase the insulation of facades and roofs, inside or outside. Changing old wooden windows and balconies unsealed.
- ADJUST TIMES AND CONSUMPTION: Avoid maximum power at certain times.
- SUBSTITUIR INSTAL·LACIONS POC EFICIENTS: Aparells amb molta demanda energètica.
- REPLACE INEFFICIENT FACILITIES: Items with high demand of energy.
ACHIEVEMENTS

- ENERGY DEMAND REDUCTION: Reducing energy demand by an average of 30%.
USE CASE: REPORT ON THE CONSUMPTION OF AN OFFICE BUILDING
OFFICE BUILDING 5.000m2: ENERGY INVOICE €135.000 / year.
ENERGY INVOICE | |
INSTALLATION CONSUMPTION | ENERGY BILL |
Climate Control and Ventilation | 64.000€ |
Indoor and Outdoor lighting | 35.000€ |
Computers, CPD, Copiers | 17.000€ |
Elevators and hoist | 8.000€ |
Water plumbing | 6.000€ |
Vending, fire prevention | 5.000€ |
TOTAL | 135.000€ |
ACTIONS AND COSTS TO ACHIEVE SAVINGS | ||||
ACTIONS | COSTS €/M2 | ESTIMATED SAVING(%) | ANNUAL SAVING(€) | ROI (YEARS) |
Change user habits | 0 | 5 | 6.750€ | IMMEDIATE |
Change vending machines | 0 | 5 | 6.750€ | IMMEDIATE |
Presence control for lighting | 15 | 10 | 13.500€ | 1-2 |
Presence control for air conditioning | 15 | 10 | 13.500€ | 1-2 |
Manage outer solar protection | 5 | 10 | 13.500€ | 2-3 |
Include outer sunscreen | 100 | 15 | 20.250€ | 3-4 |
Integration of installations | 20 | 10 | 13.500€ | 3-4 |
Change luminaries | 30 | 15 | 20.250€ | 5-6 |
Change climate machines | 250 | 15 | 20.250€ | 10-11 |
Change elevators | UD. | 5 | 6.750€ | +10 |
Facade comprehensive reform | 600* | 25 | 27.000€ | +10 |